Coverage.
Ratings.
Designated working loads shall not be increased beyond the manufacturer's ratings or original design limitations unless such increase receives the manufacturer's approval. When the manufacturer's services are not available or where the equipment is of foreign manufacture, engineering design analysis shall be performed or approved by a person accredited for certificating the equipment under part 1919 of this chapter. Engineering design analysis shall be performed by a registered professional engineer competent in the field of cranes and derricks. Any structural changes necessitated by the change in rating shall be carried out.
Radius indicator. When the rated load varies with the boom radius, the crane or derrick shall be fitted with a boom angle or radius indicator visible to the operator.
Prohibited usage.
Protective devices.
General -
Operating controls.
After October 3, 1984, overhead bridge and container gantry crane operating control levers shall be self-centering so that they will automatically move to the "off" position when the operator releases the control.
Booms. Cranes with elevatable booms and without operable automatic limiting devices shall be provided with boom stops if boom elevation can exceed maximum design angles from the horizontal.
Foot pedals. Foot pedals shall have a non-skid surface.
Access. Ladders, stairways, stanchions, grab irons, foot steps or equivalent means shall be provided as necessary to ensure safe access to footwalks, cab platforms, the cab and any portion of the superstructure which employees must reach.
Footwalks shall be of rigid construction, and shall be capable of supporting a load of 100 pounds (4.79 kPa) per square foot.
If more than 20 feet (6.1 m) in height, vertical ladders shall comply with § 1917.118 (d), (e)(1), (e)(2)(iii), and (e)(2)(iv).
Stairways on cranes shall be equipped with rigid handrails meeting the requirements of § 1917.112(e).
Operator's station.
Counterweights or ballast. Cranes shall be operated only with the specified type and amount of ballast or counterweights. Ballast or counterweight shall be located and secured only as provided in the manufacturer's or design specifications, which shall be available.
Outriggers. Outriggers shall be used according to the manufacturers' specifications or design data, which shall be available. Floats, when used, shall be securely attached to the outriggers. Wood blocks or other support shall be of sufficient size to support the outrigger, free of defects that may affect safety and of sufficient width and length to prevent the crane from shifting or toppling under load.
Exhaust gases. Engine exhaust gases shall be discharged away from the normal position of crane operating personnel.
Fire extinguisher.
At least one portable fire extinguisher of at least 5-BC rating or equivalent shall be accessible in the cab of the crane or derrick.
Rope on drums. At least three full turns of rope shall remain on ungrooved drums, and two turns on grooved drums, under all operating conditions. Wire rope shall be secured to drums by clamps, U-bolts, shackles or equivalent means. Fiber rope fastenings are prohibited.
Assembly or disassembly of boom sections. Mobile crane booms being assembled or disassembled on the ground with or without the support of the boom harness shall be blocked to prevent dropping of the boom or boom sections.
Brakes.
Rail-mounted cranes (excluding locomotive types).
For the purposes of this section, rail-mounted cranes include bridge cranes and portal cranes.
Rated load marking. The rated loads of bridge cranes shall be plainly marked on each side of the crane and in the cab. If there is more than one hoisting unit, each hoist shall have its rated load marked on it or on its load block. Marking shall be legible from the ground level.
Wind-indicating devices.
Instructions. The employer shall post operating instructions for high wind conditions in the operator's cab of each crane. Operators shall be directed to comply with these instructions. The instructions shall include procedures for responding to high wind alerts and for any coordination necessary with other cranes.
Securing of cranes in high winds.
When the wind reaches the crane's warning speed:
Stops and bumpers.
Employee exposure to crane movement. When employees may be in the vicinity of the tracks, crane trucks shall be equipped with personnel-deflecting guards.
Pedestrian clearance. If the track area is used for employee passage or for work, a minimum clearance of three feet (.91 m) shall be provided between trucks or the structures of rail-mounted cranes and any other structure or obstruction. When the required clearance is not available on at least one side of the crane's trucks, the area shall not be used and shall be marked and identified.
Warning devices. Rail-mounted cranes shall be equipped with an effective travel warning device which shall be used to warn employees who may be in the path of the moving crane.
Communications. Means of communication shall be provided between the operator's cab and the base of the gantry of all rail-mounted cranes. This requirement may be met by telephone, radio, sound-signalling system or other effective methods, but not solely by hand-signalling.
Stabilizing of locomotive cranes. Loads may be hoisted by locomotive cranes only if outriggers are in place, unless means are taken to prevent the load being carried by the truck springs of the crane.
Operations.
Guarding of swing radius. Accessible areas within the swing radius of the body of a revolving crane shall be physically guarded during operations to prevent an employee from being caught between the body of the crane and any fixed structure or between parts of the crane.
Securing mobile crane components in transit. The crane's superstructure and boom shall be secured against rotation and carried in line with the direction of travel except when negotiating turns with an operator in the cab or when the boom is supported on a dolly. The empty hook or other attachment shall be secured.
Unattended cranes. The following steps shall be taken before leaving a crane unattended between work periods:
Operating near electric power lines.
Clearance. Unless electrical distribution and transmission lines are de-energized and visibly grounded at the point of work, or unless insulating barriers not a part of or attached to the crane have been erected to prevent physical contact with lines, cranes may be operated near power lines only in accordance with the following:
Boom guards. Cage-type boom guards, insulating links or proximity warning devices may be used on cranes, but they shall not be used in place of the clearances required by paragraph (i)(5)(i) of this section.
Determination of energized lines. Any overhead line shall be presumed to be energized until the owner of the line indicates that it is not energized.
Protection for employees being hoisted.
Enclosed by a railing or other means providing protection equivalent to that described in § 1917.112(c). If equipped with open railings, the platform shall be fitted with toe boards;
Routine inspection.
Designated persons shall visually inspect each crane and derrick on each day of use for defects in functional operating components and shall report any defect found to the employer. The employer shall inform the operator of the findings.
[48 FR 30909, July 5, 1983; 62 FR 40141, July 25, 1997; 65 FR 40940, June 30, 2000]